The job
A landscaping crew needed to rebuild the verge along the noise wall at Grosvenor Street, Glandore. That meant an excavator and a truck boxing out the verge, then new loam, irrigation, mulch and planting. Four working days, with 7am starts.
The road
Anzac Highway is a state-managed arterial and one of the busiest roads into the city. Any work on or beside it needs a Department for Infrastructure and Transport permit and a traffic guidance scheme that suits the road.

How we set it up
The permit covered advisory signage and a side road closure, with no speed reduction, no lanes closed and no stopping of highway traffic. On the first day the crew ran a lateral shift to give the works room. After that, Grosvenor Street was closed at the highway, with advisory signs telling drivers the side road was shut.
One crew came from our Wingfield depot each morning in one of our own traffic utes, on site by 7am.
Why it worked
Closing the side street, rather than a lane of the highway, gave the excavator and trucks a safe, closed work area without slowing Anzac Highway itself. Drivers on the highway barely noticed the job was there.